Conversion from Standard Paver into an InLine Pave® Machine for Placing Binding Course, with Transfer Module, in Just One Working Day

The InLine Pave® concept is a highly cost-effective solution for contractors. All machine components can be used for conventional paving work at any time and after that be applied for two-layer paving “hot on hot“ on an InLine Pave® job.

Well, how long does it take to install the Transfer Module on the SUPER 2100-2 IP paver? The answer is just 6 hours. And this is what you need for fitting the Transfer Module: